Completed Projects |
![]() |
|||
CONSULTANT: Construction Control Inc. PROJECT VALUE: $1,700,000.00 SCOPE: Parking Structure Roof Slab Total Removal and Reconstruction Total area of work is approximately 45,000 square feet. Phase I - 2004 ![]() Work began August 3, 2004 with the removal of landscaping, asphalt, and existing waterproofing. ![]() Demolition of the existing slab began in mid August. ![]() Demolition continued through August and early September. ![]() Forming began in mid September. ![]() Forming continued through September into early October. ![]() Final preperation of formwork and reinforcing steel installation began on October 14th. ![]() Concrete pour for new slab took place on October 19th. ![]() The forming and shoring are being removed. ![]() Clean-up of the forming material, and shoring in underground garage began the first week of November. |